logo
Qingdao Xinmeiteng Sponge Manufacture Co.
Products
Products
Home > Products > Continuous Foaming Machine > 90 L/min Flow 56 kW Continuous Foaming Machine Cylinder Foaming Machine 3000 kg/h

90 L/min Flow 56 kW Continuous Foaming Machine Cylinder Foaming Machine 3000 kg/h

Product Details

Place of Origin: Qingdao

Brand Name: Xinmeiteng

Certification: CE

Model Number: TDP-1500

Payment & Shipping Terms

Minimum Order Quantity: 1 Set

Price: Inquiry

Packaging Details: TO BE DETERMINED

Delivery Time: 45 working days after downpayment

Payment Terms: L/C,T/T

Supply Ability: 3 sets per season

Get Best Price
Highlight:

90 L/min Foaming Flow

,

56 kW Foaming Machine

,

Vertical Cylinder Foaming

Foaming Density:
8-50 Kg/m³
Overall Dimension:
4000*6000*8500 Mm
Production Capacity:
3000 Kg/h
Foaming Diameter:
⌀1.2-1.5 M
Foaming Flow:
90 L/min
Total Power:
56 KW
Foaming Density:
8-50 Kg/m³
Overall Dimension:
4000*6000*8500 Mm
Production Capacity:
3000 Kg/h
Foaming Diameter:
⌀1.2-1.5 M
Foaming Flow:
90 L/min
Total Power:
56 KW
90 L/min Flow 56 kW Continuous Foaming Machine Cylinder Foaming Machine 3000 kg/h
TDP-1500 Cylinder Foaming Machine with 90 L/min Flow and 56 kW Power

The TDP-1500 is a vertical cylinder continuous foaming machine with a 90 L/min foaming flow and 56 kW total power. Foaming diameter is 1.2-1.5 m, production capacity is 3000 kg/h, density range is 8-50 kg/m³ and machine weight is 12000 kg. The machine is CE certified.

A foaming machine is bought for the flow it can hold, not the number on the brochure. The 90 L/min figure is what allows the block to be poured at 3000 kg/h without the pour starving at the end of the stroke, and it is the number the chemical pumps, mixing head and trough have to work with.

Power is the other half. Metering pumps, mixing head, lift, rotation and heating all draw from the same 56 kW supply, so the electrical installation is planned once rather than added to later. On a line that runs two or three shifts, that sizing is the difference between a stable pour and a machine that trips the plant supply.

TDP-1500 foaming head with the chemical feed lines connected.
TDP-1500 foaming head with the chemical feed lines connected.
The Machine at a Glance

90 L/min flow

The pour keeps pace with a 3000 kg/h line without starving at the end of the stroke.

56 kW total power

Pumps, head, lift, rotation and heating sized from one supply.

Matched metering

Flow and lift speed are set together so the block stays even.

Repeatable pour

PLC settings carry over to the next block.

  • Model: TDP-1500
  • Foaming flow: 90 L/min
  • Total power: 56 kW
  • Output: 3000 kg/h
  • Foaming diameter: ⌀1.2-1.5 m
  • Density range: 8-50 kg/m³
Chemical feed and metering pumps on the TDP-1500
Chemical feed and metering pumps on the TDP-1500.
TDP-1500 pouring head above the lifting table
TDP-1500 pouring head above the lifting table.
Setting Flow and Lift Speed Together
  1. Check the supply. Confirm the plant can carry the 56 kW load before the first run.
  2. Set the flow. Bring the metering pumps to the 90 L/min working point.
  3. Set the lift. Match the rise rate to the flow so the block fills evenly.
  4. Watch the trough. Keep the fall plate temperature steady through the pour.
  5. Finish the block. Cut off at height and let the block cure before handling.
  6. Record the settings. Store flow and lift against the recipe for the next run.

Log flow and lift speed for the first block of each shift. Two numbers on a sheet will tell you more about a density complaint than an hour at the peeler.

Why Flow Rate Decides Block Quality

A pour that loses flow at the end of the stroke leaves the top of the block short of foam. The block looks acceptable from the outside, then peels into sheets that run thin at one end. The 90 L/min working point exists so the flow holds when the chemical lines are at temperature and the head has been running for hours.

The second reason is the mixing head. Below its working flow the head does not mix the two components cleanly, and the block carries streaks that show up as hard spots after peeling. Keeping the flow at the rated point is cheaper than sorting blocks at the peeler.

Power and flow are linked. The 56 kW supply is sized for the rated flow with the pumps, lift, rotation and heating all running, so a stable pour does not depend on switching something else off.

  • Flow: 90 L/min holds through the full stroke.
  • Power: 56 kW covers pumps, head, lift, rotation and heating.
  • Result: block density stays even from base to top.
Check block weight against the foaming diameter before quoting the line: a bigger diameter does not always mean lower cost per sheet.
Technical Parameters
ParameterValue
ModelTDP-1500
Machine typeVertical cylinder continuous foaming machine
Foaming diameter⌀1.2-1.5 m
Foaming density8-50 kg/m³
Foaming flow90 L/min
Production capacity3000 kg/h
Rotation speed3000-5000 rpm
Lifting speed0-3 m/min
Total power56 kW
Machine weight12000 kg
Overall dimension4000*6000*8500 mm
CertificationCE
Core Advantages
  • 90 L/min flow: the pour keeps pace with a 3000 kg/h line without starving at the end of the stroke.
  • 56 kW total power: pumps, head, lift, rotation and heating sized from one supply.
  • 3000 kg/h output: matches the peeling and slicing capacity of a mid-size mattress foam line.
  • 8-50 kg/m³ window: one machine covers soft, medium and high density recipes.
  • PLC control: flow, lift and rotation settings repeat on the next block.
  • Low labour demand: two operators cover the pouring station once the recipe is set.
  • CE certified: export-ready guarding and electrics.
Primary Applications
  • Mattress foam plants: cylinder blocks poured for peeling into mattress and topper sheets.
  • Furniture foam: sofa and cushion foam blocks in medium and high density.
  • Shoe material foam: soft foam blocks for insole and lining stock.
  • Bra and garment padding: low density soft foam for padding stock.
  • Electronics packaging: protective foam blocks cut into inserts.
  • Automobile interior: seat and trim foam blocks poured in the same line.
TDP-1500 pouring station with trough and fall plate
TDP-1500 pouring station with trough and fall plate.
Cylinder block moving to the peeling line
Cylinder block moving to the peeling line.
TDP-1500 line during a production shift
TDP-1500 line during a production shift.
Foaming Faults and Their Causes
SymptomLikely causeAction
Block density varies top to bottomLift speed out of step with the pour rateReset the lift speed to match the 90 L/min flow
Foam sags or collapses in the centreCatalyst ratio or foam temperature off specCheck the metering recipe and the component temperature
Block diameter out of toleranceRotation speed drifting during the pourRe-check the rotation setting and the drive belt
Surface skin blistersTrough or fall plate temperature too highCheck the heating circuit and the film feed
Operation and Safety on the Pouring Station
  • Lock out the foaming head before any nozzle or trough work.
  • Keep the lifting table zone clear while the pour is running.
  • Vent the foaming room and monitor isocyanate exposure.
  • Follow the pressure relief sequence before opening any chemical line.
Daily Care of the Foaming Head
  • Flush the mixing head at the end of every shift.
  • Check the metering pump seals weekly for weeping.
  • Inspect the lifting chain and guides monthly.
  • Keep the PLC recipe backup in the maintenance file.
Packaging and Delivery

The machine travels in an export-grade wooden case with the electrics protected and the cutter or blade assembly braced separately. Machine weight is 12000 kg and the overall dimension is 4000*6000*8500 mm, so the unit is quoted against a 20ft or 40ft container depending on the line it ships with.

A packing list, wiring diagram, operation manual and CE declaration travel with every unit. Delivery is 45 working days after downpayment; installation and commissioning support is available remotely or on site.

Frequently Asked Questions
What is the foaming flow of the TDP-1500?

A: 90 L/min, matched to the 3000 kg/h output and the lift speed.

What total power does the machine need?

A: 56 kW covers the metering pumps, mixing head, lift, rotation and heating circuits.

Which follow-up machines pair with the TDP-1500 foaming line?

A: A cylinder boring machine for the centre hole and a horizontal peeler or slicer convert the poured blocks into foam sheets.

What foam density can the TDP-1500 produce?

A: Flexible polyurethane foam from 8 kg/m³ to 50 kg/m³, set through the metering pump recipe.

Send Your Foaming Requirement

Tell us the foam type, density, block diameter and the hourly output you need. We will confirm the TDP-1500 configuration, quote the line and share the delivery schedule. Mixing heads, spare metering pumps and remote commissioning support are available with every order.